Timeline For PeopleSoft V7.0/7.5
|
Task type |
Task name |
Duration |
Completion date |
Person assigned |
Status |
|
Tech |
1- Transfer modifications from V5.12 to V7. |
4 weeks |
9/20/1998 |
PS Tech Team |
Done |
|
Tech |
2- Load data to HPDEV. |
2 weeks |
8/11/1998 |
Cara, Vernon |
Done |
|
Tech |
3- Install V7 client on Payroll & Budget pc's. |
1 week |
8/17/1998 |
Vernon, Lance, Nolan |
Done |
|
Func |
4- Test PeopleTools V7 (also at tasks 8 and 9). Create fit analysis documents. |
4 weeks |
10/31/1998 |
OHR, Payroll, Budget, PS Tech Team |
Done |
|
Tech |
5- Install NT machine for 3-tier components. |
1 week |
8/10/1998 |
Osamu |
Done |
|
Tech |
6- Test Mass change (SQR) V7. |
1 week |
10/31/1998 |
Lance, Nolan |
Done |
|
Tech |
7- Create new security chart in V7. |
4 weeks |
10/31/1998 |
Vernon |
Cancelled |
|
Tech |
8- Modify V7 panels, records, peoplecode. |
3 weeks |
10/31/1998 |
PS Tech Team |
Done |
|
Tech |
9- Test Process Scheduler integrated with PeopleSoft(PNF & PAHR). |
2 weeks |
11/30/1998 |
PS Tech Team |
Done |
|
Tech |
10- PS technical training: Data Management Tools, Security, .... |
12/31/1998 |
OHR, PS Tech Team |
Done |
|
|
Tech |
11- Configure 3-tier architecture on Y2K. |
12/31/1998 |
Cara |
Done |
|
|
Tech |
12- Web enable panels using Web Client. |
6 weeks |
2/28/1999 |
OHR and PS Tech Team |
Done |
|
Tech |
13- Test 3-tier components (panels, peoplecode,...). |
2 weeks |
2/10/1999 |
OHR, PS Tech Team |
Cancelled |
|
Tech |
14- Install PS V7.5. |
2 weeks |
2/10/1999 |
Byron, Cara |
Done |
|
Tech |
15- Updgrade to V7.53, apply UH customization and test. |
15 weeks |
6/10/1999 |
PS Tech Team and Functional Team |
Done |
|
Tech |
16 a)- Upgrade to PS V7.55. |
1 week |
6/25/1999 |
Cara, Vernon |
Done |
|
Tech |
16 b)- Web enable V7.5 panels using V7.55 HTML Access. |
4 weeks |
7/12/1999 |
Byron, Lance, Diep, Cara |
Tested |
|
Func |
17 a)- Training and familiarization of V7.5 on Web. Verify data to ensure historical and current data loaded correctly. Initial testing of HR processes and procedures. FSIS and Data Warehouse conversion testing. |
7 weeks |
10/8/1999 |
Functional Team and PS Tech Team |
Done |
|
Tech |
17 b)- Test the move to production(UHV7TGT). |
4 weeks |
(6/25/1999-)7/23/1999 |
Vernon, Cara |
Done |
|
Tech |
17 c)- Install V7.56 and test Web Client. |
3 weeks |
9/3/1999 |
PS Tech Team |
Done |
|
Tech |
17 d)- Decide to implement Web access or not: Web access using IE is chosen for rollout. |
9/10/1999 |
ITS Director |
Done |
|
|
Func |
18 a)- Implement beta user testing. Iterative process. As beta users test V7.5 make modifications as necessary. |
4 weeks |
11/5/1999 |
Functional Team and PS Tech Team |
Done (slow performance) |
|
Func |
18 b)- Define Security Definition for V7.5. |
9/10/1999 |
Functional Team |
Done |
|
|
Tech |
18 c)- Install PeopleTools V7.57 to resolve Web client problems. |
11/26/1999 |
PS Tech Team |
Done |
|
|
Tech |
18 d)- Beta test on V7.57 Web client. |
1/28/2000 |
Functional Team and PS Tech Team |
Done (slow performance) |
|
|
Tech |
18 e)- Perform controlled testing. |
3/10/2000 |
ITS |
Done |
|
|
Tech |
18 f)- Install memory leak patch and perform controlled testing. |
4/10/2000 |
PS Tech Team |
Done |
|
|
Tech |
18 g)- Perform beta test to validate memory leak. |
5/26/2000 |
Functional Team and PS Tech Team |
Done |
|
|
Func |
19 a)- Create end user procedures, documentation, and training manual. Train parallel users. |
3-4 weeks |
Functional Team |
||
|
Tech |
19 b)- Install new machine. - Ready for testing. - Ready for production. |
6/1/2000 |
Vernon, Cara |
Done |
|
|
Tech |
19 c)- Create database for parallel testing UHxx(similar to task 17b). |
1 week |
6/15/2000 |
PS Tech Team |
Done |
|
Tech |
19 d)- Implement V7.5 Security. |
4 weeks |
9/30/2000 |
Vernon |
Done for Beta test |
|
Func |
20- Implement parallel test. Parallel testing, modify software, retest, modify, etc. |
4 weeks |
9/30/2000 |
Functional Team and PS Tech Team |
Done |
|
Func |
21- Implement training for all users (large group). |
2-5 weeks |
3/28/2001 |
Functional Team and PS Tech Team |
Done |
|
Tech |
22- Move to production. |
4/2/2001 |
PS Tech Team |
Done |