Task name

Estimation of time

Person assigned

Completion date

Status

1- Identify Leave panels of V7.5 baseline.

1 week

Nolan

3/22/1999

Done

2- Identify Leave records of V7.5 baseline.

1 week

Nolan

3/29/1999

Done

3- Set up Web server for V7.5 DEMO75.

2 days

Cara

3/25/1999

Done

4- Create or modify UH Leave request record and panels with Security settings.

5 weeks

Diep

10/31/1999

80%

5- Implement Workflow.

3 weeks

Diep, Cara

10/31/1999

50%

6- Make Web enabled Leave panels.

1 week

Lance

10/31/1999

60%

7- Write SQR programs to populate Civil Service data to PS tables for leave system.

2 weeks

Elisa

12/15/1999

Done

8- Load current Leave Accrual data to UHLEAVE.

1 week

Lance

4/15/2000

Done

9- Load Leave transactions from current system to PS.

3 weeks

Lance

4/15/2000

Done

10- Test Leave Request Panels and make modifications.

4 weeks

Functional Team and Tech Team

   

11- Analyze Leave Calculation.

3 weeks

Functional Team and Tech Team

   

12- Write SQR program for Leave Accruals Earnings and Balance.

4 weeks

Lance

   

13- Develop/implement scanning function.

4 weeks

Lance, Lloyd

   

14- Beta user test.

       

Last update: 12 August 2000