Tentative Timeline For Leave System Implementation
|
Task name |
Estimation of time |
Person assigned |
Completion date |
Status |
|
1- Identify Leave panels of V7.5 baseline. |
1 week |
Nolan |
3/22/1999 |
Done |
|
2- Identify Leave records of V7.5 baseline. |
1 week |
Nolan |
3/29/1999 |
Done |
|
3- Set up Web server for V7.5 DEMO75. |
2 days |
Cara |
3/25/1999 |
Done |
|
4- Create or modify UH Leave request record and panels with Security settings. |
5 weeks |
Diep |
10/31/1999 |
80% |
|
5- Implement Workflow. |
3 weeks |
Diep, Cara |
10/31/1999 |
50% |
|
6- Make Web enabled Leave panels. |
1 week |
Lance |
10/31/1999 |
60% |
|
7- Write SQR programs to populate Civil Service data to PS tables for leave system. |
2 weeks |
Elisa |
12/15/1999 |
Done |
|
8- Load current Leave Accrual data to UHLEAVE. |
1 week |
Lance |
4/15/2000 |
Done |
|
9- Load Leave transactions from current system to PS. |
3 weeks |
Lance |
4/15/2000 |
Done |
|
10- Test Leave Request Panels and make modifications. |
4 weeks |
Functional Team and Tech Team |
||
|
11- Analyze Leave Calculation. |
3 weeks |
Functional Team and Tech Team |
  | |
|
12- Write SQR program for Leave Accruals Earnings and Balance. |
4 weeks |
Lance |
||
|
13- Develop/implement scanning function. |
4 weeks |
Lance, Lloyd |
||
|
14- Beta user test. |