Peoplesoft V7.5 Upgrade Plan

PeopleSoft V7.5 Upgrade Plan

 

   

Task

Person assigned

Duration

Date projected

Status

Phase I: Preparing for Upgrade

    1- Organize the Upgrade

Diep

5 days

2/1/99

Done

Phase II: Installing Software

    2- Install PeopleSoft Software

Cara, Byron

5 days

2/10/99

Done

    3- Copy V7 database (UHDEV2K) to UHUPG2K

Cara, Vernon

1 day

2/12/99

Done

    4- Clean up UHUPG2K

        a)Update Statistics
        b)Audit reports
        c)Counts report
        d)Clean PSOJCHNG
        e)Delete obsolete view

Vernon

4 days

2/15/99

Done

Phase III: Upgrade PeopleTools

 

15 days

3/5/99

 

    5- Upgrade PeopleTools System Tables

Vernon

   

Done

    6- Convert Query Definition

Vernon, Diep

   

Done

    7- Load Base Data, Messages and SQR String Data

Vernon

   

Done

    8- Verify the Version Numbers

Cara, Diep

   

Done

    9- Backup UHUPG2K

Cara

   

Done

    10- Run Grant and Synonym Scripts

Vernon

   

Done

    11- Compare PPLTLS75

Vernon

   

Done

    12- Export/Copy PPLTLS75 Project

Cara, Vernon, Diep

   

Done

    13- Load Model Definitions and Stored Statements

Cara, Diep

   

Done

    14- Audit the Database

Vernon

   

Done

Phase IV: Comparing, Reporting and Copying the Upgrade

   

3/23/99

 

    15- Run Rename Scripts

Vernon

1 day

 

Done

    16- Backup UHUPG2K

Cara

1/2 day

 

Done

    17- Run Upgrade Compare

        a)Remove Unused Language-Coded Items
        b)Run Upgrade Compare

Vernon, Diep

3 days

 

Done

    18- Review Compate Reports

Diep

10 days

 

Done

    19- Override Upgrade Compares

Diep

5 days

 

Done

    20- Run Upgrade Copy

        a)Turn Off Change Control
        b)Run Upgrade Copy

Diep, Vernon

3 days

 

Done

    21- Copy the Non-Comparison Upgrade Projects

Diep

1 day

 

Done

    22- Backup UHUPG2K

Vernon

1/2 day

 

Done

Phase V: Using SQL Alter and Create

 

10 days

4/6/99

 

    23- Perform Pre-Alter Table Cleanup

        a)List Tablespace Names
        b)Review EMPLMT_SGBL_SBR

Vernon, Diep

   

Done

    24- Using SQL to Alter Tables and Fields

Vernon

   

Done

    25- Use SQL to Create Tables

Vernon

   

Done

    26- Update Tablespace Names

Vernon

   

Done

Phase VI: Converting Data

Vernon, Diep

12 days

4/20/99

 

    27- Refresh Data From UHPROD

     

Cancelled

    28- Load New Tables with Prompt Data

     

Done

    29- Backup UHUPG2K

     

Done

    30- Use SQL to Alter Tables Without Deletes

     

Done

    31- Copy Data for Renamed Record Fields

     

Done

    32- Run Data Conversion Scripts

     

Done

    33- Backup UHUPG2K

     

Done

    34- Use SQL to Alter Tables With Deletes

     

Done

    35- Use SQL to Create Views

     

Done

    36- Use SQL to Create Indexes

     

Done

    37- Setup for Post-Alter Conversion

     

Done

    38- Perform Post-Alter Conversion

     

Done

    39- Load Message and Application System Data

     

Done

Phase VII: Clean Up and Testing Database

       

    40- Cleanup and Manual Changes

Diep, Vernon

5 days

5/1/99

Done

    41- Audit UHUPG2K

Vernon

2 days

5/4/99

Done

    42- Apply UH Customization

Lance, Diep

15 days

5/31/99

Done


Last update: 1 May 2000